Design & Manufacture Case Study

Production live in 4 weeks without tooling

Delivery model: Design & Manufacture (D&M)


Executive summary

  • Sector: Industrial / field-deployed systems

  • Requirement: 50 technical support units to ship alongside a primary product

  • Constraint: No tooling permitted due to compressed schedule

  • Timeline: Design complete in 2 weeks. Production live in 4 weeks

  • Outcome: Units delivered on schedule without tooling investment


Timeline

  • Week 0: Brief received

  • Week 2: Design validated through functional prototypes

  • Week 4: Production complete and units delivered


The challenge

The client required a batch of ruggedised technical support units to deploy in parallel with a primary product launch.
The schedule ruled out tooling, and any delay would have impacted field deployment and customer commitments.

The work could not be absorbed internally without disrupting core programmes.


The solution

We delivered the programme under our Design & Manufacture model.

Two functional prototypes were designed, built, and validated within the first two weeks.
Production was achieved using fabrication, additive manufacture, and off-the-shelf components to eliminate tooling lead time.

Custom wiring looms were designed and built in parallel, allowing assembly and quality assurance to proceed without delay.


Outcome

  • 50 units delivered on schedule to support the main product launch

  • No tooling investment required, preserving flexibility and cash

  • Third successful product delivered for the same client

The programme achieved its delivery window without creating long-term manufacturing commitments or internal disruption.


Why This Worked

  • Single point of accountability

  • Control matched to responsibility

  • Defined entry and exit conditions

This was not outsourcing.
It was containment.

Take the Design & Manufacture test