Factory setup and run Case Study

Factory operational in 12 weeks for a defence programme

Delivery model: Factory Setup & Run (FSR)


Executive summary

  • Sector: Defence

  • Requirement: Time-limited production outside the client’s core operations

  • Constraint: Regulated environment with zero tolerance for delivery failure

  • Timeline: Factory operational in 12 weeks

  • Outcome: Programme delivered to plan and closed without residual cost or disruption


Timeline

  • Week 0: Programme definition and site selection

  • Week 6: Facility layout, systems, and supply chain in place

  • Week 12: Factory fully operational and producing

  • Programme end: Facility closed and exited cleanly


The challenge

The client faced a production obligation that could not be absorbed internally without disrupting core programmes.
Traditional outsourcing introduced unacceptable control and delivery risk.

The requirement was clear: deliver production quickly, under regulation, without creating permanent organisational overhead


The solution

We delivered the programme under our Factory Setup & Run model.

A dedicated production facility was designed, established, and operated by Corcoran Yates.
We recruited and managed the production team, implemented quality systems, and ran day-to-day operations for the duration of the programme.

From the outset, the factory was designed for both delivery and exit.


Outcome

  • Production facility live and delivering within 12 weeks

  • Programme delivered without disrupting the client’s core operations

  • No long-term facility, headcount, or cost burden retained by the client

The programme met its delivery obligations and closed cleanly at completion.